When the members of Shrawley Village Hall were looking for a more affordable way of running the community’s shared space, they were pleased to have found Caplor Energy. We understand that community spaces are run by hard working volunteers which is why we make the process as straightforward as possible. We will design a system with the building users in mind and meet with members to go through any Government incentive applications. This may be solar PV to reduce electricity bills or a solar thermal system to provide hot water. You can have a carbon neutral wet heating system with a biomass boiler or if you’re community building has land, a ground source heat pump may be a good option. All of which are eligible for RHI payments.
Technical Summary
- System size (Installed capacity) 4.00 kWp
- Expected annual generation: 3,434 kWh
- Expected annual CO2 savings: 1.95 tCO2e
- Estimated savings in electricity purchases: £395.32 / yr
- Estimated Generation Tariff (FiT): £511.67 / yr
- Estimated effective annual revenue £986.66 / yr
- Initial Rate of Return (exc. VAT) 11.5%
- Expected System Payback: 8.7 years